A project manager’s company operates in a high-technology area requiring the integration and sharing of several functional specialties.The project manager is considering the appropriate organizational structure for a new project.The likely choice would be-( )
A.Matrix 
B.Tight matrix
C.Functional
D.Projectized

A.矩阵
B.强矩阵
C.职能型
D.项目型

参考答案

A

答案解析

暂无解析