In order to manage a project effectively, work should be broken down into small pieces.Which of the following does NOT describe how far each task should be broken down?( )
A.Can be completed in under 80 hours
B.Can not be logically subdivided further
C.Is done by one person
D.Can be realistically estimated

A.可以在80小时以下完成。
B.不能再进一步进行逻辑细分了。
C.可由一个人完成。
D.可以进行实际估算。

参考答案

C

答案解析

暂无解析