What is the document that forms the basis for an agreement between the project team and the project customer by identifying both the project objectives and the major project deliverables?( )
A.Implementation Plan
B.Configuration Management Plan
C.Scope Statement 
D.Work Authorization Plan

A.执行计划
B.配置管理计划
C.范围说明书
D.工作授权计划

参考答案

C

答案解析

暂无解析