Which of the following is not a function of contract administration?( )
A.Change management
B.Specification interpretation
C.Determination of breach of contract
D.Selection of the project manager

A.变更管理
B.规格说明
C.合同违约的界定
D.项目经理的选择

参考答案

D

答案解析

暂无解析