In which type of contract arrangement is the customer at greatest risk of absorbing excessive cost overruns?( )
A.Cost Plus Percentage of Cost
B.Time and Materials
C.Firm Fixed Price with Economic Price Adjustment
D.Fixed Price Incentive Firm Target

A.成本百分比加成
B.工时和原材料
C.按照经济价格指数调整的实盘固定价
D.固定价实盘目标奖励

参考答案

A

答案解析

暂无解析