In which type of contract arrangement is the contractor least interested in controlling costs?( )
A.Cost Plus Percentage of Cost
B.Time and Materials
C.Cost Plus Fixed Cost
D.Fixed Price Incentive Firm Target

A.成本百分比加成
B.工时和原材料
C.固定成本加成
D.固定价实盘目标奖励

参考答案

A