单选题 信息系统项目管理师
2010-11-14

Changes may be requested by any stakeholder involved with the project,but changescan be authorized only by _____(73)_____.
(73)A.executive ITmanager
B.project manger
C.change control board
D.project sponsor

参考答案

暂无

答案解析

暂无解析