An activity has an early start date-of the 10th and a late start date of the 19th.The activity also has a duration of 4 days.There are no nonworkdays.From the information given, what can be concluded about the activity?( )
A.Total float for the activity is 9 days.
B.The early finish date of the activity is the end of the day on the 14th.
C.The late finish date is the 25th.
D.The activity can be completed in 2 days if the resources devoted to it are doubled

A.该项工作的总浮动日期为9天
B.该项工作最早完成日期为14号当天结束时
C.该项工作最迟完成的日期为25号
D.如果投入该项工作的资源增加一倍的话,该项工作可以在两天内完成

参考答案

A

答案解析

计算总的浮动时间的公式是用活动完成最迟的时间减去最早的时间,即19-10=9