The three most common techniques for developing project cost estimates are: ( )
A.Budgetary, team-based and parametric 
B.Analogous, top-down and bottom-up 
C.Analogous, parametric and direct 
D.Analogous, parametric, and bottom-up

A.预算式,团队式的和参数式
B.类比式,由上而下式和由下而上式
C.类比式,参数式和直接式
D.类比式,参数式和由下而上式

参考答案

D

答案解析

暂无解析