Upon completion of 75% of the project, the original schedule and cost estimate that were submitted at the inception of the project are referred to as the: ( )
A.Baseline 
B.Budgeted costs 
C.Estimates upon completion costs 
D.Scheduled costs

A.基准计划书
B.预算成本
C.完工成本估算
D.安排计划成本

参考答案

A

答案解析

暂无解析