Your project experiences an internal failure of a major component causing project overruns.The action necessary to bring this defect into compliance with specifications is considered: A.Rework
B.Warranty repairs
C.Quality control
D.Preventative

A.返工
B.维修保证
C.质量控制
D.预防

参考答案

A

答案解析

暂无解析