As a project manager, it is conceptually important to provide quality assurance at what point in projects?( )
A.During the initial planning phase
B.Throughout the project
C.At identified checkpoints
D.During project quality reviews

A.在初始规划阶段
B.在项目所有阶段
C.在确认的检查点上
D.在项目质量评审期间

参考答案

B

答案解析

暂无解析