Which of the following least affects a contractor’s ability to perform the contracted activities after the contract is signed?( )
A.A poor definition of contract deliverables
B.The extent of project sub-contracting
C.The complexity of the contracted effort
D.The contract type

A.对合同交付物的定义出现问题
B.项目分包的程度
C.所签约的工作复杂性
D.合同类型

参考答案

D

答案解析

暂无解析