单选题
PMP
2008-10-24
Which of the following would you do if you wanted the contractor to start work on a project immediately?( )
A.Issue a letter contract, but follow up as soon as possible with some type of a final contract
B.Sign a Time and Materials contract for the entire effort
C.Negotiate a Firm Fixed Price contract
D.Negotiate a cost sharing arrangement
A.先签发一封合同意向书,然后尽快形成某种类型的最终合同书
B.对整个任务工作,签一份个工时和原材料合同
C.谈判达成实盘固定价合同
D.谈判达成成本分摊办法
参考答案
A
答案解析
暂无解析
你可能感兴趣的试题
A.请求建议书(RFP)
B.担保式邀标
C.谈判协商价格
D.采购货单
A.对所要求的产品或服务,制定清楚简明的描述说明书
B.制定你所愿支付的价格
C.向所有潜在的有资格的卖主公开竞标
D.为投标者提供一次预竞标会议
A.设计规格要求
B.功能规格要求
C.绩效要求
D.项目规格要求