Project stakeholders are individuals and organizations that are actively involved in the project, or whose interests may be positively or negatively affected by the project.In the event of differences among the stakeholders, preference should be given to whom? ( )
A.The customer
B.The performing organization
C.The community where the project takes place
D.The sponsor

A.客户
B.实施的组织
C.项目发生所在社区
D.业主

参考答案

A

答案解析

暂无解析