单选题
PMP
2008-10-24
You have estimated and scheduled your project based on the team members you have been assigned and developed the BCWS baseline.However, you have now been assigned new team members who are more experienced and higher salaried than those on which you based your initial estimate.The most probable impact on project performance would be: ( )
A.Negative CV, negative SV
B.Negative CV, positive SV
C.Positive CV, negative SV
D.Positive CV, positive SV
A.负的成本偏差CV,负的进度偏差SV
B.负的成本偏差CV, 正的进度偏差SV
C.正的成本偏差CV,负的进度偏差SV
D.正的成本偏差CV,正的进度偏差SV
参考答案
B
答案解析
暂无解析
你可能感兴趣的试题
A.由下而上
B.类比
C.预算
D.修正标准
A.人工,原材料,其它直接费用,管理储备
B.人工原材料,管理储备,管理费用
C.管理储备人工,其它直接费用,管理费用
D.人工原材料, 其它直接费用,管理费用