Once the logic of a network is laid out, the project manager will conduct a forward pass and then a backward pass through the network.Doing this will provide information on
the and the lead to the identification of the .( )
A.Slack for each activity, critical path
B.Slack for each activity, high-risk activities
C.Manpower shortages, high risk activities
D.High risk activities, non-critical paths

A.每项活动的时差,关键路线
B.每项活动的时差,高风险活动
C.人力短缺,高风险活动
D.高风险活动,非关键路线

参考答案

A