单选题
PMP
2008-10-24
Once the logic of a network is laid out, the project manager will conduct a forward pass and then a backward pass through the network.Doing this will provide information on
the and the lead to the identification of the .( )
A.Slack for each activity, critical path
B.Slack for each activity, high-risk activities
C.Manpower shortages, high risk activities
D.High risk activities, non-critical paths
A.每项活动的时差,关键路线
B.每项活动的时差,高风险活动
C.人力短缺,高风险活动
D.高风险活动,非关键路线
参考答案
A
答案解析
暂无解析
你可能感兴趣的试题
A.专家判断
B.限制因素
C.假定
D.资源能力
A.资源限制的进度
B.资源分配进度
C.资源平衡进度
D.资源定量化进度