Which method shown below would normally not be used for shortening the schedule?( )
A.Crashing
B.Changing the scope
C.Performing activities in parallel rather than in series
D.Resource leveling

A.赶工
B.变更范围
C.以并行方式而不是序列方式来实施进行活动
D.资源平衡

参考答案

D

答案解析

暂无解析