If a project manager emphasizes those areas where he is in agreement with the functional manager and down plays other conflicts, the project manager can be said to be using which of the following to address the conflict: ( )
A.Withdrawal
B.Smoothing
C.Compromising
D.Confrontation

A.回避
B.协商处理
C.妥协处理
D.正面对抗

参考答案

B