单选题
PMP
2008-10-24
When evaluating the possible solutions and tradeoffs to resolve a project conflict, the project conflict, the project manager should: ( )
A.Consider only lessons learned from previous projects
B.Ignore the potential of compromising the sponsor’s objectives, and corporate strategic plan
C.Fully consider possible impact on schedule, cost, risk, and performance
D.Consider only the effect on resources consumed and project resource consumption for that project
A.只考虑以前项目的经验教训
B.不考虑是否有协调业主的目标与公司的策略计划的可能性
C.完全充分考虑到对进度,成本风险和绩效的影响
D.只考虑对所用资源的影响及该项目的整个资源消耗情况
参考答案
C
答案解析
暂无解析