单选题
PMP
2008-10-24
The requirements and functional specifications have been completed and the acceptance test strategy is now in development.At what point in the project should the project manager plan for events not happening in accordance with the project plan? ( )
A.When the unanticipated events occur, because this approach saves you valuable time
B.Contingency planning should occur throughout the project life cycle
C.Only during the development of the risk management plan
D.Contingency planning occurs mainly in the Design Phase
A.当未预料到的事件发生的时候由于这种方法节省你宝贵的时间
B.意外事件规划应该贯穿于整个项目生命周期
C.仅在风险管理计划制定期间
D.意外事件规划主要地在项目设计阶段进行
参考答案
B
答案解析
暂无解析
你可能感兴趣的试题
A.90%
B.45%
C.15%
D.33%
A.设计
B.开发/实行
C.构思立项
D.结束
A.事件发生的可能性乘以事件发生的结果
B.事件发生的可能性乘以风险事件发生次数
C.风险事件发生次数乘以事件发生的结果
D.最大风险的事件发生可能性乘以最小风险的事件的发生的结果