A random quality audit has been called on your project.What is typically the objective of such an audit?( )
A.Identify lessons learned that can improve project performance
B.Determine the cause of configuration management problems
C.Determine why products are not meeting specifications
D.Find those that are under performing on the project

A.总结出经验教训,以便改进项目绩效
B.确定框图管理问题的原因
C.确定产品为什么没有满足规格
D.确定哪些人没有达到项目绩效要求

参考答案

A