某框架结构工程,柱、有梁板浇捣均使用C30混凝土,砾石粒径为40mm,板厚100mm,第三层层高4米,结构平面及配筋如下图所示。请根据《房屋建筑与装饰工程工程量计算规范》(GB50854-2013)的规定计算柱、梁、板的混凝土工程量。

参考答案
暂无
答案解析
工程量计算:
Vz1=0.5×0.5×4×6=6m³
Vz2=0.4×0.4×4×2=1.28m³
小计:V柱=7.28m³
VKL1=0.25×(0.4-0.1)×(7.2-0.5×2)×2=0.93m³
VKL2=0.25×(0.4-0.1)×(3.6-0.2-0.15)=0.24m³
VKL3=0.25×(0.5-0.1)×(6-0.5)=0.55m³
VKL4=0.25×(0.4-0.1)×(6-0.5-0.4)×2=0.77m³
小计:V梁=2.49m³
V板=[(7.2+0.50)×(6+0.5)-0.5×0.5×6-0.4×0.4×2]×0.1=4.82m³
V有梁板=V梁+V板=7.31m³
Vz1=0.5×0.5×4×6=6m³
Vz2=0.4×0.4×4×2=1.28m³
小计:V柱=7.28m³
VKL1=0.25×(0.4-0.1)×(7.2-0.5×2)×2=0.93m³
VKL2=0.25×(0.4-0.1)×(3.6-0.2-0.15)=0.24m³
VKL3=0.25×(0.5-0.1)×(6-0.5)=0.55m³
VKL4=0.25×(0.4-0.1)×(6-0.5-0.4)×2=0.77m³
小计:V梁=2.49m³
V板=[(7.2+0.50)×(6+0.5)-0.5×0.5×6-0.4×0.4×2]×0.1=4.82m³
V有梁板=V梁+V板=7.31m³